Need help?

MBA641 Strategic Project Management Report Sample

MBA641 Strategic Project Management

Your task

Individually, you are required to prepare a Statement of Work (SOW) based on your tender for the STH BNK by Beulah project that you have prepared in the first assessment.

Assessment Description

The purpose of this assessment is to foster students’ ability to evaluate and determine project viability, including the analysis required in the selection process. Students will also be given an opportunity to demonstrate the necessary evaluative criteria for the success of projects based on an organisation’s goals, strategy and standards.

Assessment Instructions

Presume that the project stakeholders accepted your tender from Assessment 1. Now you are required to prepare the Statement of Work (SOW) submission based on the information contained in the case study and the details in the first assessment. As the STH BNK by Beulah project is a real-life case study, you are expected to complement your work with additional research on the project and its site.

Your Statement of Work submission must contain all the required elements, including an introduction, scope, location, main tasks, milestones, deliverables, schedule, standards, success criteria, requirements, budget outlines, any other relevant information, and a closing statement. Please ensure that you attend the live assessment webinar, as your subject coordinator will provide you with an SOW template that you must use in this assessment.

While this is a written analysis, you can include any tables, analysis or diagrammatical elements you deem appropriate. You will be required to use a minimum of 15 sources in your Statement of Work, 5 of which must come from academic journals or textbooks. These sources must be presented as in-text citations and a reference list adhering to the Kaplan Harvard Referencing Style. Wikipedia and other ‘popular’ sites are not to be used.

Solution

Statement of Work
 
Introduction
 
Name of Project
Beulah’s Sth Bnk Project
 
Background 

Beulah’s Sth Bnk Project is a Melbourne-based project that aims to build the tallest tower in Australia. An investment of $2 billion is made in this project and the Victorian government has approved the budget for the compassion of the project in an efficient manner. The project aims to enhance the livelihood of the urban society of Melbourne. Future generations shall be overwhelmed by the project and the project includes two skyscrapers. In this project, an area of 270,000 sqm is covered and one of the buildings consists of 102 storeys which makes the height 366 meters. As per the MBA Assignment Experts Another skyscraper of height 251 meters has 59 floors. International design and world-class innovation are done in this building, attracting many stakeholders. The project aims to provide an innovative place for the executions of Melbourne to stay and explore. The Future Melbourne 2026 Plan is followed in this project so as to build an inclusive and sustainable society (City of Melbourne, 2022). This project also follows the principle of sustainability where it follows several green strategies to reduce the amount of construction waste (Katsonis, 2019). The sustainable building will enhance Australia's economic stability as it is a highly-priced construction where each apartment shall be sold at a price of $35 million. The aim of this project is to establish living destinations for the citizens of Melbourne where they can work, stay and explore new ideas amidst the green environment. The project will include not only the skyscrapers but also retail areas, commercial offices, resort and cultural spaces, childcare facilities, and health and wellness centres. 4,700 employees will be given jobs during the construction of this project (DESIGN-BUILD NETWORK, 2020). 

Purpose

The purpose of the project is to provide a sustainable living area to the citizens of Australia. The project follows a sustainable mode of construction and encourages its customers to explore new ways of living amidst the green while staying in these apartments (Bocken et al., 2019). The rooms will have large windows that discourage using artificial lights and electricity while staying in these apartments. Similarly, the major purpose of the project is also to provide a luxurious lifestyle to the citizens of Melbourne. The significance of this project is its ability to encourage the citizens to experience an innovative lifestyle where they can live, work and explore (Sthbnk.com 2022). Fresh air shall be available for the residents of these apartments as the skyscrapers will have vertical gardens. The project not only aims to construct apartments but it will create a sustainable society for the upgradation of the lifestyle of Melbourne. In this world of globalization, the level of pollution is increasing and there is a need for sustainable buildings which can encourage citizens to live amidst nature. This project aims to engage in sustainable living and create a society that is based on sustainable principles. similarly, the purpose of this project is to create a living space which has all the amenities a person needs in his daily life including recreation centres, fitness spaces and retail stores. 

Scope of Work 

 

To Be Done

 

Resources Needed

Outcome

Time Involved

General Steps

Contracting with suppliers and vendors to get quick supplies of raw materials

Contact details of sustainable suppliers

Finalizing contracts with sustainable suppliers so they can supply construction-based material before the project starts.

2 months

The initial step is to ask for quotations from suppliers, which the project executive must review. after reviewing and negotiating, the contractor who uses the sustainable mode of business has to be chosen for the project

The hiring of project managers

The human resource managers who can take interviews with project managers and hire them

Project managers are required to divide the roles and responsibilities of the construction-based project.

1 month

Interested candidates can send their biodata to the hr manager and the experienced and capable candidates shall be called over for an interview.

The hiring of skilled employees who can do the main construction job

Experienced project managers who can analyze the capabilities of the employees before hiring them.

Employees shall work effectively do the building of skyscrapers and the amenities such as clubs, swimming pools, healthcare facilities and office rooms.

1 month

The interview shall be taken so as to analyze the experience and skill set of employees.

The hiring of architects and engineers

Experienced human resource managers who can evaluate the cornice and capabilities of architects and engineers.

Architects and engineers shall be responsible for designing skyscrapers and sustainable society.

1 month

Work experience of architects and engineers shall be evaluated before they are recruited for the project.

Training of employees so that they can be educated about the significance of the project.

Financial resources to set up a training infrastructure.

Employee training will make them more effective in the workplace and the project can be completed in an efficient manner.

1 month

All new employees, architects, engineers and project managers shall be given brief training in online mode so that they can understand the project mission and vision.

Deployment of construction technologies to build tall skyscrapers

Financial resources and technical team to evaluate which technologies will be effective in the compassion of the project.

Modern technologies shall enhance the speed of construction.

15 days

A list of modern tools and technologies shall be made and it will be sent to the suppliers so that machines can be implemented before the project is initiated.

Contracting with gardeners to plant trees in vertical gardens

Financial resources so as to pay them adequate wages.

Gardeners shall plant green and long-living trees in every apartment's vertical garden so residents can inhale fresh air.

15 days

Gardeners shall be recruited after a short discussion with them about the types of plants that all be planted in the vertical gardens.

Location 

 

Site

Duration

 

Office: 98 Shirley Street PIMPAMA QLD 4209 AUSTRALIA

 

4 years

Remote Location: Carlton

Preston

Victoria – 3053

Australia

 

2 years

Deliverables 

Deliverable

Objective

Due Date

 

Design drawings

 

To complete the drawing of designs of skyscrapers within 15 days of project initiation

18.08.22

Supply of high-quality construction materials

 

To get supplies of the best quality products to ensure the highest quality construction of buildings

02.09.22

Sustainable construction

 

To make contracts with sustainable suppliers

25.08.22

Schedule 

Phases

 

Start

Finish

Initiation of project discussion 

15.09.22

15.11.2022

Planning of project-based roles and responsibilities of construction-based project

18.11.22

18.02.23

Execution of project deliverables

18.10.23

18.10.25

Performance of the construction-based activities where skyscrapers and other buildings will be constructed. 

22.09.22

12.08.27

Monitoring of construction-based activities

22.09.24

22.09.27

Milestones

 

Milestones

Start Date

Finish Date

 

Discussion on the initiation of the project and design makes for the construction

15.09.22

15.12.2022

Building of the two skyscrapers

 

15.02.23

15.10.2025

Construction of amenities such as retail stores

 

18.10.23

18.10.25

Construction of health and fitness centre

 

18.10.23

18.10.25

 resort and culture space

 

22.09.24

22.09.26

Commercial offices

22.09.24

22.09.26

Monitoring of project and completion

22.12.23

22.10.27

Tasks 

Activity

 

Duration

Team member

Initiation of project discussion

 

2 months

Project managers, sponsors, employees, architects and engineers

Designing of project

 

1 month

Architects and engineers

 

Building of skyscrapers, vertical buildings, commercial offices, retail stores and health and fitness centres

 

4 years

Project managers and employees

Monitoring and completing the project

5 years

Project managers and engineers


Reporting and Communications

The reporting of the project will be done on a daily basis. Every employee will report the daily activities to their respective project managers. It is the responsibility of project managers to monitor the activities and compile the daily activities of employees into a document. As a consequence, this document prepared by the project manager is the report of the progress of construction-based activities which shall be reviewed by stakeholders and will reflect the mode of transparency among employees and sponsors of the project. mode of communication will be physical settings and emails. The report will be delivered over emails regularly and physical meetings will be held once a month to keep the progress of the project. No data manipulation will be done to maintain authenticity in a project's progress. All activities will be referred to secondary qualitative data that will be gained from research articles and journals. The previous case studies of the construction-based project will be referred to gain ideas about sustainable construction and complete the project of Sth Bnk on time. Communication is necessary as it helps in maintaining transparency and accountability with stakeholders. The online mode of communication is quick and that is the reason for choosing this mode of communication over physical meetings. It is time-consuming to meet physically every week; hence the physical meeting is scheduled once a month only. Monitoring of projects has to be done effectively by the project managers so that any issues faced while constructing the skyscrapers and other buildings can be immediately informed to the project owners. Such a strategy will help the project managers and employees to solve the issues in an efficient manner.

Standards and Testing

Define Success Criteria

The success criteria for this construction project are to be analysed by considering different elements associated with the project (Frefer et al., 2018). The cost of the project was one aspect that is to be considered for measuring the success of the project (Amora and Juanzon, 2022). The total budget for the construction work is 2 billion. The cost of materials and other supportive accessories are to be enlisted here. Completion of the project within the cost is the primary criterion for measuring success (Gunduz and Yahya, 2018; Tam et al., 2020). The overall project is scheduled to be completed within 5 years. Maintaining the timeframe is essential here as a long period will result in an increment in the cost of the project. Thus, the predetermined profitability after selling the property cannot be maintained. Implementation of the safety measure is also important to consider here for measuring profitability (Kim et al., 2019; Karakhan and Gambatese, 2018). However, at least, the environmental aspects are also to be considered for having maximum control of sustainability (Wang et al., 2018; Thacker et al., 2019). The Australian laws related to the environment and safety are to be considered for having maximum control of the sustainable development of the construction project.

Requirements

The construction work will require the general tools that are mandatory for any construction work. They are, Circular saw Cordless drills and Concrete mixers. Apart from these, equipment such as brick hammers, and blister are also required. The information is also to be managed through a special channel. The inclusion of software is also required for having control of the overall criteria. The inclusion of these elements has been essential to building proper communication in all different departments. Thus, any software supporting business information management is to be included

Still in Dilemma? See what our users have to say about our services.

student rating
Management

Essay: 10 Pages, Deadline: 2 days

They delivered my assignment early. They also respond promptly. This is excellent. Tutors answer my questions professionally and courteously. Good job. Thanks!

flag User ID: 9***95 United States

student rating
Accounting

Report: 10 Pages, Deadline: 4 days

After sleeping for only a few hours a day for the entire week, I was very weary and lacked the motivation to write anything or think about any suggestions for the writer to include in the paper. I am glad I chose your service and was pleasantly pleased by the quality. The paper is complete and ready for submission to the professor. Thanks!

flag User ID: 9***85 United States

student rating
Finance

Assignment: 8 Pages, Deadline: 3 days

I resorted to the MBA assignment Expert in the hopes that they would provide different outcomes after receiving unsatisfactory results from other assignment writing organizations, and they genuinely are fantastic! I received exactly what I was looking for from this writing service. I'm grateful.

flag User ID: 9***55

student rating
HR Rrecruiter

Assignment: 13 Pages, Deadline: 3 days

Incredible response! I could not believe I had received the completed assignment so far ahead of the deadline. Their expert team of writers effortlessly provided me with high-quality content. I only received an A because of their assistance. Thank you very much!

flag User ID: 6***15 United States

student rating
Management

Essay: 8 Pages, Deadline: 3 days

This expert work was very nice and clean.expert did the included more words which was very kind of them.Thank you for the service.

flag User ID: 9***95 United States

student rating
Thesis

Report: 15 Pages, Deadline: 5 days

Cheers on the excellent work, which involved asking questions to clarify anything they were unclear about and ensuring that any necessary adjustments were made promptly.

flag User ID: 9***95 United States

student rating
Economics

Essay: 9 Pages, Deadline: 5 days

To be really honest, I can't bear writing essays or coursework. I'm fortunate to work with a writer who has always produced flawless work. What a wonderful and accessible service. Satisfied!

flag User ID: 9***95

student rating
Taxation

Essay: 12 Pages, Deadline: 4 days

My essay submission to the university has never been so simple. As soon as I discovered this assignment helpline, however, everything improved. They offer assistance with all forms of academic assignments. The finest aspect is that there is also an option for escalation. We will get a solution on time.

flag User ID: 9***95 United States

student rating
Management

Essay: 15 Pages, Deadline: 3 days

This is my first experience with expert MBA assignment expert. They provide me with excellent service and complete my project within 48 hours before the deadline; I will attempt them again in the future.

flag User ID: 9***95 United States

GET A FREE ASSISTANCE

Still Finding MBA Assignment Help? You’ve Come To The Right Place!